Building Our Dream Home: September/October 2021

September & October house building was slow but looking back we got some big things taken care of. 

September 16th

September was uneventful.  We got our propane tank in.


And air conditioner up and running.


Bonus room split up and running.



September 17th

All door knobs ordered and arrived from Amazon.  I had to go through and use a router on each door to make all the pieces fit the door.  If you didn't know... your belly button is the perfect pace to hold your screwdriver if you are putting door knobs on all by yourself. 


October 2nd

October was more productive than September.  Finally, after being ready for cabinets since July 1st when drywall was completed, we got our first set of cabinets installed. 


They might not have all been correct but at least we had something. 
Kitchen....


There are supposed to be spice racks in between where the stove top is.


Pantry...


There is supposed to be a mini fridge in the pantry.  The way the cabinets are built he put a door on the far cabinet.  That door wont be able open once the mini fridge is put in. 




Front steps completed


Got one of the "eyebrows" stained


October 3rd

Steps into the garage are complete!


October 6th

Flooring started.  This is the boys bathroom.


October 7th

Half bath tile in!  It's SO pretty!!!


Got a start on the Master bathroom!


Laid out the upstairs bathroom.


Where the tub will sit in the Master...


October 13th

Started to tile the boys shower


Finished the upstairs bathroom floor.


Started grouting all the tile. 


October 16th

Getting the Master shower prepped for tile.


October 22nd

Got the island in so that we could have countertops measured.


Also got great room book shelves...


... and our bathroom vanities.




We had him move the bottoms pieces around to make room for my spice racks.


The boys bathroom cabinet and vanities came too!



Sink placed to make sure the countertops would sit right.


Having to cut out spots to find outlets.


October 26th

Main flooring install started!


It looks so good!


Adding the bar legs to the island.



Bathtub installed!


October 27th

Putting in the kitchen sink faucet.


October 28th

Working on getting the pellet ice machine in and working.


Liam proud of the progress.


Looking better with the flooring in!



Got the newel post in and waiting on the stair treads to be delivered. 



 